Åëåêòðîíåí áþëåòèí
On Line Bulletin
holder_point.gif (43 bytes)
 

ñ ïîäêðåïàòà íà - supported by
Ïð Ôîíäàöèÿ “Ïîìîù çà áëàãîòâîðèòåëíîñòòà â Áúëãàðèÿ” “- Èíñòèòóò çà óñòîé÷èâè îáùíîñòè
Th Bulgarian Charity Aid Foundation Institute for Sustainable Communities

áðîé 1: íîåìâðè 2000
áðîé 2: äåêåìâðè 2000
áðîé 3: ÿíóàðè 2001
áðîé 4: ìàðò 2001

áðîé 5: àïðèë 2001
áðîé 6: þëè 2001
Áðîé 7: þëè 2001
Áðîé 8: àâãóñò 2001
Áðîé 9: àâãóñò 2001

 

 

The European corridor No 4, financed by EU funds, is going to destroy an important area for conservation of biodiversity in Europe

Struma Highway planning through the “Kresna” CORINE Site (Kresna gorge) in Bulgaria.

Za Zemiata/ CEE Bank Watch Network

Description of the project:

Financial memoranda 98 and 99 of the PHARE Cross Border Cooperation (CBC) program finance the project “E-79 Detailed design of motorway Sofia-Kulata”. The total amount of the grant is 3 342 450 Euro. Implementation agency (IA) is the Ministry of Regional Development and Public Works (MRDPW). General Road Administration (GRA) is responsible in front of the CBC IA for the operational management of the project. On 1 September 1999 a tender procedure for project “E-79 Detailed design of motorway Sofia-Kulata” was opened. Candidates were 6 firms from Italy, United Kingdom and Denmark. An Italian firm, SPEA Ingegneria Europea won the tender and the contract was signed on 09 March 2000 with 20 months implementation period.
The project “E-79 Detailed design of motorway Sofia-Kulata” included preparation of feasibility study, EIA, detailed design and tender dossier for motorway
Sofia-Kulata (consisted of two motorways -motorway “Ljulin” and motorway “Struma”). The project is divided in three stages: 1) feasibility study 2) design and tender document of 2 lots of the Struma motorway 3) design and tender documents of 1 lot of Struma motorway and the whole Ljulin motorway. The first two stages have to be carried out together and completed for 8 months and the third stage for 12 months.

About the implementation of the project we (environmental NGOs) know that:

In the beginning of June SPEA prepared introductory report.
On 25 November 2000 SPEA received EIA report prepared by the Bulgarian firm “OMEX” –subcontractor, which means that SPEA finished the feasibility study, which was the first part of the project. By this moment no alternative options had been designed for the motorway in the region of Kresna gorge (see below). NGOs suppose that requirements for examination and evaluation of alternative roadbeds for the motorway, different from already designed by GRA in 1997,are not included in the Terms of Reference prepared by GRA. At least we are sure that such obligatory requirements are not included for the part of motorway, which has to pass through the region of Kresna gorge.

What we did in order to find information and to be involved in the decision making process:

Environmental NGOs have been concerned by the design and construction of the Struma motorway since the beginning in 1997 (see attached Kresna campaign.rtf and Eu letter sent.rtf). At least 15 Bulgarian NGOs participate in the campaign for protection of Kresna gorge region (recognized as a CORINE site Kresna) - a very important natural area which has to become part of the European Ecological Network NATURA 2000 after Bulgaria becomes member of EU. All roadbeds of the motorway designed in 1997 by GRA pass trough this region and pose a threat to nature which is a violation of Bulgarian and European legislation (Bulgarian Nature Protection Act, Bern Convention, Directives 92/43 and 79/409). The motorway trough the gorge will also have a significant impact on the town of Kresna situated at the exit of the gorge. NGOs wrote many letters and had many meetings with representatives of the Bulgarian Ministry of Environment and Waters (MEW) and several meetings with representatives of DG Environment in EU commission. In all our statements since 1997 we had one main demand – to be protected Kresna CORINE site, which mean Struma motorway to pass outside this area. In the same time authority responsible for implementation of the motorway, even do not have alternative which do not cause the damaging and destroying of the CORINE site Kresna. Since 1997 the design of the motorway and preparation of EIA report have been conducted without any public participation. The position of environmental NGOs in Bulgaria and possible damages for Kresna CORINE site and Kresna town have been neglected.

Unfortunately, the practice of GRA and MRDPW to not give information to the public, to not allow public participation and not consider NGOs
request for designing real alternatives continued after FUNDS FOR THE DESIGN WERE PROVIDED BY PHARE CBC and therefore by EU. Not
only the Bulgarian government but also EU institutions did not give full and relevant information about this project.

Here is a short history of the attempts of NGOs to participate in the decision making process and to obtain information about government and EU activities related to the design of the motorway during 2000.

On 14 February 2000 NGOs sent a letter to Mr. Evgeni Chachev Minster of the Regional Development and Public Works with a request for meeting and with an
appeal to consider NGOs suggestion to design the alternatives outside the Kresna gorge. Until then NGOs did not know anything about the opened tender procedure
for project “E-79 Detailed design of motorway Sofia-Kulata” financed by PHARE CBC. There were no any announcements in the Bulgarian media that such a
procedure will be conducted. No answer to our letter was received.

  • After a short announcement in newspapers at the end of March that a contract for designing the Struma motorway had been signed with an Italian firm, NGOs sent
    a letter with a request for information to GRA on 13 April 2000. We asked GRA about projects or contracts for designing of the Struma motorway, financial
    provision of this contracts and whether GRA had included in Terms of Reference a requirement for designing alternatives outside the gorge. In their answer from 10
    May 2000 we learned that the firm SPEA is engaged for preparation of the feasibility study of the Struma motorway and PHARE CBC is supporting this project. No
    answer to our question about alternative roadbeds of the motorway. No answer to our question to obtain official documents indicating what are the
    intentions of our government.
  • In June several informal meeting with specialists from SPEA were made to find out more about the project. Most of the information was refused with the
    explanation that the owner of the information is GRA. In these informal talk we found that SPEA did not intend to developed alternatives outside the gorge.
  • We wrote two letters-request for development of alternative routes outside Kresna CORINE site, signed by 6 NGOs, (10 July 2000): first to MEW and second to
    MRDPW and GRA. In a letter from 21 July 2000 GRA (as an answer) wrote that SPEA had presented an introductory report and GRA had “proposed” to the
    firm to develop alternatives which do not damage the territory with international conservation importance. No confirmation that this will really happen, that
    developing of the alternatives is included in the contract and Terms of Reference was given to SPEA.
  • On 24 July 2000 we wrote an official letter to SPEA with request for meeting. We wanted to present them our concerns and to exchange information. No answer
    was received.
  • In relation to the public meeting-discussion which we intended to organize in Kresna on 10 August, we requested from GRA (“the owner of the documentation”) to
    provide a copy of the maps of the potential route. No answer was received.
  • At the meeting organized by us in Kresna we invited a big range of specialists from MEW, MRDPW, GRA, and European delegation in Bulgaria, and scientists
    working in the region. Only one representative from GRA, Mr. Hristov, was presented (see attached protocol meeting.rtf). The latter used every possibility to
    reassure people that “it is too early, and when different alternatives are ready they will be discussed with local people”. At the meeting NGOs
    representatives asked him for obtaining the whole SPEA’s introductory report and to make it public. Mr. Hristov promised to give the whole report. Later, after the
    next request in written form (15 August 2000) made by NGOs, only a part of the report was given. The maps and probably many other important
    sections were not given. This is the only case, when GRA gave any official document to the NGOs and the public.
  • On 16 October 2000 we officially asked GRA for the Terms of Reference made by GRA for SPEA. Information was canceled, with the demand for the legal
    status of our organization to be presented.
  • In informal talk with head of OMAX (firm conducting EIA) we found that EIA is ready and will be presented in front of SPEA on 25 October 2000
  • The European Delegation in Sofia was interested in the public meeting and expressed a wish to receive a protocol from the meeting. We presented the protocol (in
    Bulgarian and English) to Mrs. Teodora Mircheva on our meeting on 1 November 2000 in the European Delegation. On this meeting we invited the Mayor and
    Deputy-Mayor of Kresna (see memo.rtf). At that meeting NGOs submitted a letter for obtaining information about the EU commission requirements for feasibility
    studies financed by EU funds and about the feasibility study given to SPEA. No answer was received.
  • Due to Mrs. Teodora Mircheva a second meeting was organized with representative of GRA, SPEA, OMAX and head of PHARE Program – Mrs. Vesselina
    Ljubenova, hosted by the European Delegation. During the meeting Mrs. Vesselina Ljubenova expressed the statement that Terms of Reference of the firm SPEA will
    be changed and will include development of the alternative outside Kresna CORINE site. But till end of 2000 there is no evidence that this has happened.
    Bulgarian institutions and PHARE are again in silence.
  • On 23 November 2000 NGOs again sent a letter to GRA with request for access the following information: Terms of Reference given to SPEA, documents and
    papers already prepared by SPEA, all information related to the preparation of the EIA report. Till the end of 2000 no answer was received.

    Lack of consultation with local people.

    During the preparation of the feasibility study local people have not been informed about the plans for the Struma motorway to go through the gorge and Kresna
    town. The only source of information for them was the meeting organized by NGOs.
    No discussion with local people for the possible route-beds was held.

    In spite of all promises for development of the alternative route outside the Kresna CORINE site in the beginning of December the Mayor of Kresna was asked to come to Sofia in GRA where he was told that the decision for the construction of the motorway is already taken and there is only one option “through the gorge and the town”.

 

 

Back